1. Test the agreed functions in every room
Work from the quotation and room schedule. Check switches, touchscreens and the app. Test curtain directions, lighting groups, dimming and compatible AC controls. Then run Morning, Away and Bedtime scenes with real household situations in mind. Record each outstanding adjustment with an owner and completion date.
2. Demonstrate internet and power recovery behaviour
Ask which controls work locally and which depend on the internet or cloud services. Agree a supervised demonstration and document the result. Also discuss what happens after a normal power interruption: which devices restore their previous state and which need another command? Do not assume every automation or notification has the same dependency.
3. Review ownership and user permissions
Identify the owner account, household users and any installer remote access. Agree how to recover access when a phone is replaced and how to remove a user. Keep credentials in an appropriate secure place. A shared administrator login is not a substitute for a clear access policy.
4. Check the network and integrated alerts
Try app controls in rooms and outdoor areas included in the network scope. If leak detection, intercom or access control are included, request a safe test following the manufacturer’s instructions. Confirm who receives an alert, what response is configured and what happens when the phone has no connection.
5. Collect documents and configuration backups
Ask for equipment details, circuit labels, relevant drawings and operating instructions. For KNX, agree access to the current ETS project export and associated security information as part of the contract. Supporting files can be included within an ETS project. A dated backup and clear update process support future maintenance.
6. Train the household; 7. confirm after-sales support
Let the actual users practise everyday controls and a manual fallback. Then confirm warranty scope, exclusions, support contact and how to request changes. Separate correcting an agreed defect from adding new features. A useful handover ends with a tested system, an agreed snag list and people who know how to use the home.
Your practical checklist
- Room-by-room functional results
- Recorded offline and recovery behaviour
- Owner accounts and agreed installer access
- Dated drawings and configuration backups
- Training, warranty details and support contact
Frequently asked questions
Should I receive the KNX project file?
Agree the project export and security-information handover or retention arrangement in the contract. Do this before installation, not only after a problem appears.
Can a phone demonstration replace testing the wall switches?
No. Test every control method included in your scope because each may have different dependencies.
What if work remains at handover?
Document the outstanding items, responsibilities and completion dates before final acceptance.